Logs Away

Well, we're still at the 5 logs to go mark. The last 5 are about 20 feet in
the air, so we've had a lot of setting up to do. Eight sets of scaffolding
(2 stacks of 4), a 9th layer of scaffolding and a pulley system later we are
all set to go. By the time we got it set up Monday night it was getting
dark and Rodney had to work late Tuesday night, so perhaps we'll make some
progress tonight.

We are also hoping that our fancy new beam cutting saw will arrive today.
Once it is here, we can get started on the roof!